Hickory
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Jackson County. First named in the release with data as of June 1, 2026.
Described as new. The quoted wording calls this substation new. “New Hickory 345kV Switchyard” — project 59959 title, as the utility reported it
Reported complete. Project 59959 is on the Completed tab (actual in-service 2026-05), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.
No HIFLD substation record has this name in this county (a record of the same name exists in another county).
Generation interconnection requests filed in Jackson, TX: ERCOT queue, 6 active of 6. Same county, not the same substation.
Location
Jackson County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: Already in service: TPIT 59959 is on the Completed tab, actual 2026-05. Rename: TPIT calls it 'New Hickory 345kV Switchyard' ('Build a new New Hickory 345 switchyard'), so the station's name may be 'New Hickory' rather than 'Hickory'.
Sources: ERCOT TPIT, project 59959 (release 39, 2026-10-01), sheet CompletedTPIT100126NoCost. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| New Hickory 345kV Switchyard Build a new New Hickory 345 switchyard to connect New Hickory Solar plant. This new Switchyard will loop into the existing Elm Creek to STP circuit 2 transmission line. ERCOT project 59959 · utility no. T-0303; S-0940 |
CPS/NO Tier 4 |
In-Service Completed tab |
345 | May 2026 actual 2026-05 |
5323 to 5133, 5915 Jackson County |
Hickory |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 59959 | Status as reported | Planned → In-Service |
| July 13, 2026 | 59959 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 59959 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 59959 | Projected in-service date | Jan 2026 → May 2026 |
| February 1, 2025 | 59959 | Projected in-service date | Oct 2025 → Jan 2026 |
| June 1, 2024 | 59959 | Projected in-service date | Oct 2024 → Oct 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.