San Marcos
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Hays County. First named in the release with data as of May 12, 2023.
Hayscounty as printed
138kV
LCRATSCutility
3projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Hays, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Lockhart - San Marcos Transmission Line Conversion The five LCRA TSC-owned transmission line sections from Lockhart to San Marcos will be converted to 138-kV (T220 San Marcos to Camp Gary to Robert Brown Jr., T519 Robert Brown Jr. to Clear Fork, and T601 Clear Fork to Lockhart). ERCOT project 73106 · RTP 2023-SC11 |
LCRATSC Tier 4 |
Planned Completed tab |
138 | May 2026 actual 2026-05 |
Lockhart to San Marcos Caldwell / Hays County |
Lockhart, San Marcos |
| Redwood - San Marcos Transmission Line Upgrade LCRA TSC will upgrade T200 Redwood - San Marcos 138-kV transmission line to obtain a higher operational rating. ERCOT project 73838 · RPG 24RPG034 |
LCRATSC Tier 4 |
Planned Completed tab |
138 | May 2025 actual 2025-05 |
Redwood to San Marcos Hays County |
Redwood, San Marcos |
| San Marcos - Strahan Transmission Line Upgrade LCRA TSC will upgrade T230 San Marcos - Strahan 138-kV transmission line to achieve a higher operational rating. ERCOT project 85959 |
LCRATSC Tier 4 |
Planned Completed tab |
138 | May 2025 actual 2025-04 |
San Marcos (7192) to Strahan (7193) Hays County |
San Marcos, Strahan |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 73106 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 73106 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 73838 | Moved between tabs | Future → Completed |
| June 1, 2025 | 85959 | Moved between tabs | Future → Completed |
| October 1, 2024 | 73838 | Projected in-service date | Dec 2025 → May 2025 |
| October 1, 2024 | 85959 | First listed | on the Future tab |
| June 1, 2024 | 73106 | Projected in-service date | Sep 2026 → May 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.