SR Bertron
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2015.
Harriscounty as printed
138kV
CNPutility
1projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| DIABOX Customer Load Addition with related line upgrades Upgrade Ckt.21E MOMENT to SOLMER to SR Bertron to increase thermal limits ERCOT project 81006 |
CNP Tier 4 |
Planned Current-year planned tab |
138 | Aug 2026 | SOLMER to SR Bertron/MOMENT Harris County |
SOLMER, SR Bertron, MOMENT |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 81006 | Projected in-service date | Jul 2026 → Aug 2026 |
| July 13, 2026 | 81006 | Projected in-service date | Jun 2026 → Jul 2026 |
| July 13, 2026 | 81006 | Projected in-service date | Mar 2026 → Jun 2026 |
| June 1, 2026 | 81006 | Projected in-service date | Jan 2026 → Mar 2026 |
| February 1, 2026 | 81006 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 81006 | Projected in-service date | May 2026 → Jan 2026 |
| June 1, 2024 | 81006 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.
Site Scanner