Substation Scout

Japhet

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of October 1, 2022.

Harriscounty as printed
138kV
CNPutility
1projects listed

Described as new. The quoted wording calls this substation new. “new Japhet substation” — project 70628 description, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Location

Harris County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: TPIT 70628 is on the Planned tab with ISD 2026-12.

Sources: ERCOT TPIT, project 70628 (release 39, 2026-10-01), sheet PlannedTPIT100126NoCost. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Japhet 138kV Distribution Sub and Upgrades
Upgrade portions of 69kV Ckt.12 Garden Villas to Bringhurst to Clinton. Install new 138kV Japhet distribution substation. Move 69kV Bringhurst substation load to new Japhet substation and retire Bringhurst substation. Retire portions of Ckt.12 and convert the remaining portions of Ckt.12 to 138kV service. Loop new Japhet substation to create new 138kV Ckt.13 University to Japhet to Clinton.
ERCOT project 70628
CNP
Tier 4
Planned
Current-year planned tab
138 Dec 2026 Japhet to University/Clinton
Harris County
Japhet, University, Clinton

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202670628Projected in-service dateAug 2026 → Dec 2026
June 1, 202670628Projected in-service dateMay 2026 → Aug 2026
February 1, 202670628Moved between tabsFuture → Current-year planned
February 1, 202670628Projected in-service dateDec 2026 → May 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.