Downtown

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2015.

Harriscounty as printed
69, 138kV
CNPutility
3projects listed

A HIFLD substation record has the same name and county: DOWNTOWN (HARRIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Hyde Park to Downtown Ckt.32A Upgrades
Upgrade Hyde Park to Downtown Ckt.32A
ERCOT project 64499
CNP
Tier 4
Planned
Future tab
69 Feb 2027 Downtown to Hyde Park
Harris County
Downtown, Hyde Park
Upgrade to increase thermal limits as part of FRM upgrades
Upgrade Hyde Park to Downtown Ckt.32A to increase thermal limits as part of FRM upgrades
ERCOT project 87479G
CNP
Tier 4
Conceptual
Current-year planned tab
69 Jul 2025 Hyde Park to Downtown
Harris County
Hyde Park, Downtown
Facility Ratings Methodology (FRM) Upgrades
Upgrade Hyde Park to Downtown Ckt.32A to increase thermal limits as part of FRM upgrades
ERCOT project 90232I
CNP
Tier 4
Conceptual
Current-year planned tab
138 Jul 2025 Hyde Park to Downtown
Harris County
Hyde Park, Downtown

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202664499Moved between tabsCurrent-year planned → Future
October 1, 202664499Projected in-service dateDec 2026 → Feb 2027
July 13, 202687479GStatus as reportedPlanned → Conceptual
February 1, 202664499Moved between tabsFuture → Current-year planned
February 1, 202690232IStatus as reportedPlanned → Conceptual
June 1, 202587479GMoved between tabsFuture → Current-year planned
June 1, 202590232IMoved between tabsFuture → Current-year planned
February 1, 202590232IFirst listedon the Future tab
October 1, 202487479GFirst listedon the Future tab
June 1, 202464499Projected in-service dateMay 2026 → Dec 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.