Clodine

Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of October 1, 2015.

Harriscounty as printed
138kV
CNPutility
5projects listed

A HIFLD substation record has the same name and county: CLODINE (HARRIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Ckt.25B Clodine to Roark to increase thermal limits.
ERCOT project 109607
CNP
Tier 4
Planned
Future tab
138 May 2028 Clodine to Roark
Harris County
Clodine, Roark
Jeanetta Auto Upgrades
Upgrade Ckt.25B Roark equipment and reconductor near Roark substation to increase thermal limits
ERCOT project 78490C · RPG 23RPG031
CNP
Tier 3
Planned
Current-year planned tab
138 Oct 2026 Clodine to Roark
Harris County
Clodine, Roark
Jeanetta Auto Upgrades
Reconductor Ckt.25B Clodine to Roark TR8 tap to increase thermal limits.
ERCOT project 78490D · RPG 23RPG031
CNP
Tier 3
Planned
Current-year planned tab
138 Oct 2026 Clodine to Roark
Harris County
Clodine, Roark
Clodine Reconfiguration for Houston IV BESS (24INR0584)
Install one new generator lead at the existing Clodine W670/W680 breaker position for Houston IV BESS.
ERCOT project 90180A
CNP
Tier 4
In-Service
Completed tab
138 Jun 2026
actual 2026-04
Clodine to Generator
Harris County
Clodine, Generator
Clodine Reconfiguration for Houston IV BESS (24INR0584)
Reposition Ckt.25B Clodine to Roark to the existing W670/W710 breaker position.
ERCOT project 90180B
CNP
Tier 4
In-Service
Completed tab
138 Jun 2026
actual 2026-04
Clodine to Roark
Harris County
Clodine, Roark

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109607First listedon the Future tab
July 13, 202690180AMoved between tabsCurrent-year planned → Completed
July 13, 202690180AStatus as reportedPlanned → In-Service
July 13, 202690180BMoved between tabsCurrent-year planned → Completed
July 13, 202690180BStatus as reportedPlanned → In-Service
June 1, 202690180AProjected in-service dateMay 2026 → Jun 2026
June 1, 202690180BProjected in-service dateMay 2026 → Jun 2026
February 1, 202678490CMoved between tabsFuture → Current-year planned
February 1, 202678490CProjected in-service dateMay 2026 → Oct 2026
February 1, 202678490DMoved between tabsFuture → Current-year planned
February 1, 202678490DProjected in-service dateMay 2026 → Oct 2026
February 1, 202690180AMoved between tabsFuture → Current-year planned
February 1, 202690180BMoved between tabsFuture → Current-year planned
February 1, 202578490CProjected in-service dateMay 2025 → May 2026
February 1, 202590180AFirst listedon the Future tab
February 1, 202590180BFirst listedon the Future tab
June 1, 202478490CFirst listedon the Future tab
June 1, 202478490DFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.