ADLONG

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of October 1, 2023.

Harriscounty as printed
138kV
CNPutility
1projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand ADLONG substation” — project 86009, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Expand ADLONG substation for XE Murat Storage (24INR0329)
Expand facilities at customer-owned ADLONG substation for XE Murat Storage (24INR0329). Utilize existing generator lead Eastgate to XE Murat Solar.
ERCOT project 86009
CNP
Tier 4
In-Service
Completed tab
138 Aug 2026
actual 2025-03
Eastgate to ADLONG
Harris County
Eastgate, ADLONG

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202686009Moved between tabsCurrent-year planned → Completed
October 1, 202686009Status as reportedPlanned → In-Service
October 1, 202686009Projected in-service dateJul 2026 → Aug 2026
July 13, 202686009Projected in-service dateJun 2026 → Jul 2026
July 13, 202686009Projected in-service dateMar 2026 → Jun 2026
June 1, 202686009Projected in-service dateJan 2026 → Mar 2026
February 1, 202686009Projected in-service dateAug 2025 → Jan 2026
October 1, 202586009Moved between tabsCompleted → Current-year planned
October 1, 202586009Projected in-service dateFeb 2025 → Aug 2025
June 1, 202586009Projected in-service dateJan 2025 → Feb 2025
February 1, 202586009Moved between tabsFuture → Completed
February 1, 202586009Projected in-service dateDec 2024 → Jan 2025
October 1, 202486009First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.