Janka
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Hardeman County. First named in the release with data as of July 13, 2026.
Described as new. The quoted wording calls this substation new. “Janka: Construct New 345 kV Station” — project 91774 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Hardeman, TX: ERCOT queue, 8 active of 8 · SPP queue, 0 active of 1. Same county, not the same substation.
Location
Hardeman County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Sources: ERCOT TPIT, projects 110569, 91774 (release 39, 2026-10-01), sheet FutureTPIT100126NoCost. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Janka: Add Reactive Support Add Reactive Support at the Janka 345 kV Station ERCOT project 110569 |
ETT Tier 4 |
Conceptual Future tab |
345 | May 2029 | Janka Hardeman County |
Janka |
| Janka: Construct New 345 kV Station Interconnect the Evergrid load to the new Janka 345 kV station on the Edith Clarke to Tesla 345 kV line ERCOT project 91774 · utility no. TP2025126 |
ETT/AEP TNC Tier 4 |
Planned Future tab |
345 | Mar 2028 | Janka Hardeman County |
Janka |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 110569 | First listed | on the Future tab |
| July 13, 2026 | 91774 | Projected in-service date | Apr 2027 → Mar 2028 |
| June 1, 2026 | 91774 | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 91774 | Projected in-service date | Jan 2026 → Apr 2027 |
| February 1, 2026 | 91774 | Projected in-service date | Jun 2025 → Jan 2026 |
| October 1, 2025 | 91774 | Projected in-service date | Jan 2025 → Jun 2025 |
| June 1, 2025 | 91774 | First listed | on the Current-year planned tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.