Parkway
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Guadalupe County. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: PARKWAY (GUADALUPE County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Guadalupe, TX: ERCOT queue, 16 active of 20. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Parkway Substation T1 Replacement Replace T1, 20 MVA with a 40 MVA 138-13.09 kV transformer ERCOT project 20TPIT0000 |
GVEC Tier 4 |
Planned Future tab |
138 | Feb 2027 | Parkway Guadalupe County |
Parkway |
| Parkway Substation T2 Replacement Replace T2, 20 MVA with a 40 MVA 138-13.09 kV transformer ERCOT project 22TPIT0000 |
GVEC Tier 4 |
Planned Current-year planned tab |
138 | Dec 2026 actual 2025-08 |
Parkway Guadalupe County |
Parkway |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| February 1, 2026 | 22TPIT0000 | Moved between tabs | Future → Current-year planned |
| February 1, 2025 | 20TPIT0000 | Projected in-service date | May 2027 → Feb 2027 |
| October 1, 2024 | 20TPIT0000 | Projected in-service date | Jun 2026 → May 2027 |
| October 1, 2024 | 22TPIT0000 | Projected in-service date | Jun 2025 → Dec 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.