Substation Scout

Parkway

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Guadalupe County. First named in the release with data as of February 1, 2015.

Guadalupecounty as printed
138kV
GVECutility
2projects listed

A HIFLD substation record has the same name and county: PARKWAY (GUADALUPE County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Guadalupe, TX: ERCOT queue, 16 active of 20. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Parkway Substation T1 Replacement
Replace T1, 20 MVA with a 40 MVA 138-13.09 kV transformer
ERCOT project 20TPIT0000
GVEC
Tier 4
Planned
Future tab
138 Feb 2027 Parkway
Guadalupe County
Parkway
Parkway Substation T2 Replacement
Replace T2, 20 MVA with a 40 MVA 138-13.09 kV transformer
ERCOT project 22TPIT0000
GVEC
Tier 4
Planned
Current-year planned tab
138 Dec 2026
actual 2025-08
Parkway
Guadalupe County
Parkway

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202622TPIT0000Moved between tabsFuture → Current-year planned
February 1, 202520TPIT0000Projected in-service dateMay 2027 → Feb 2027
October 1, 202420TPIT0000Projected in-service dateJun 2026 → May 2027
October 1, 202422TPIT0000Projected in-service dateJun 2025 → Dec 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.