Substation Scout

Valley Switch

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Grayson County. First named in the release with data as of July 13, 2026.

Graysoncounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Grayson, TX: ERCOT queue, 4 active of 4. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Paris Switch - Valley Switch 138 kV Line
Paris Switch - Valley Switch 138 kV Line Upgrade
ERCOT project 110647 · utility no. M3323 · RPG 25RPG040 · RTP 2024-NC31
ONCOR
Tier 1
Planned
Future tab
138 May 2033 Paris Switch to Valley Switch
Fannin / Grayson County
Paris Switch, Valley Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110647Projected in-service dateAug 2033 → May 2033
July 13, 2026110647First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.