McDonald Road
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Glasscock County. First named in the release with data as of June 1, 2015.
Glasscockcounty as printed
138kV
ONCORutility
3projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Glasscock, TX: ERCOT queue, 18 active of 20. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Pastores 138 kV Switch Construct a new 138 kV Switch ERCOT project 88035 · utility no. R8817 |
ONCOR Tier 4 |
Planned Completed tab |
138 | May 2026 actual 2026-05 |
McDonald Road to Catclaw/Mudstone Glasscock County |
McDonald Road, Catclaw, Mudstone |
| Chalk 69 kV Substation Conversion to 138 kV Add Permian Basin Reliability Plan Upgrade ID L20G. Construct a new Chalk 138-kV substation at the existing Chalk 69-kV substation and loop the existing McDonald Road – Navigation 138-kV line into Chalk ERCOT project 98878 · utility no. PB_L20_G |
ONCOR Tier 3 |
Planned Future tab |
138 | Dec 2027 | Prong Moss to McDonald Road Howard / Glasscock County |
Prong Moss, McDonald Road |
| McDonald Road - Polecat Creek 138 kV Rebuild Rebuild the 13.75 mile McDonald Road Switch - Polecat Creek Switch 138 kV Line ERCOT project 98953 · utility no. R8207 · RPG 25RPG035 |
ONCOR Tier 3 |
Planned Future tab |
138 | Dec 2028 | McDonald Road to Polecat Creek Glasscock County |
McDonald Road, Polecat Creek |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 88035 | Moved between tabs | Current-year planned → Completed |
| June 1, 2026 | 98953 | Projected in-service date | Dec 2027 → Dec 2028 |
| February 1, 2026 | 88035 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 98878 | First listed | on the Future tab |
| October 1, 2025 | 98953 | First listed | on the Future tab |
| February 1, 2025 | 88035 | Projected in-service date | Dec 2025 → May 2026 |
| October 1, 2024 | 88035 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.
Site Scanner