Pearsall

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Frio County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.

Friocounty as printed
69, 138kV
AEP TCC, STECutility
4projects listed

A HIFLD substation record has the same name and county: PEARSALL (FRIO County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Frio, TX: ERCOT queue, 4 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Pearsall Station
Upgrade Pearsall Station equipment for full auto xfmr ratings. (Upgrade station to breaker and a half is complete)
ERCOT project 71319
STEC
Tier 4
Planned
Future tab
138 Jun 2027 Pearsall to Pearsall
Frio County
Pearsall
Upgrade Pearsall Auto
ERCOT project 76790
STEC
Tier 4
Planned
Future tab
138 May 2032 Pearsall to Pearsall
Frio County
Pearsall
Big Foot to Pearsall: Convert to 138 kV
Convert the Big Foot to Dilley 69 kV line to 138 kV, rebuild the Dilley to Dilley Switch 69 kV line, and reroute the Big Foot to Dilley line from Dilley to Dilley Switch
ERCOT project 80315 · utility no. 3821 · RPG 23RPG024
AEP TCC
Tier 4
Planned
Future tab
138 Feb 2028 Big Foot to Pearsall
Frio County
Big Foot, Pearsall
Dilley Switch to Pearsall: Convert to 138 kV, Reroute from Dilley to Dilley Switch, Rebuild Dilley to Dilley Switch 69 kV, and Double Circuit Dilley Switch to Pearsall with Dilley to Dilley Switch
Convert the Big Foot to Dilley 69 kV line to 138 kV, rebuild the Dilley to Dilley Switch 69 kV line, and reroute the Big Foot to Dilley line from Dilley to Dilley Switch
ERCOT project 80317 · utility no. 3822 · RPG 23RPG024
AEP TCC
Tier 4
Planned
Future tab
138 Feb 2028 Dilley Switch to Pearsall
Frio County
Dilley Switch, Pearsall

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Big Foot to Pearsall: Rebuild 69 kV line
Rebuild 69 kV line from Big Foot to Dilley
ERCOT project 55603 · utility no. 3821
AEP TCC
Tier 3
Planned
Cancelled tab
69 Nov 2022
actual 2025-05
Big Foot to Pearsall
Frio County
Big Foot, Pearsall

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202671319Moved between tabsCurrent-year planned → Future
October 1, 202671319Projected in-service dateDec 2026 → Jun 2027
October 1, 202680315Projected in-service dateDec 2027 → Feb 2028
October 1, 202680317Projected in-service dateDec 2027 → Feb 2028
February 1, 202671319Moved between tabsFuture → Current-year planned
February 1, 202671319Projected in-service dateMay 2026 → Dec 2026
October 1, 202571319Moved between tabsCurrent-year planned → Future
October 1, 202571319Projected in-service dateDec 2025 → May 2026
October 1, 202580315Projected in-service dateDec 2026 → Dec 2027
October 1, 202580317Projected in-service dateDec 2026 → Dec 2027
June 1, 202555603First listedon the Cancelled tab
June 1, 202571319Moved between tabsFuture → Current-year planned
February 1, 202571319Projected in-service dateDec 2024 → Dec 2025
February 1, 202576790Projected in-service dateMay 2027 → May 2032
October 1, 202471319Moved between tabsCompleted → Future
October 1, 202471319Projected in-service dateMay 2024 → Dec 2024
October 1, 202480315Projected in-service dateSep 2026 → Dec 2026
October 1, 202480317Projected in-service dateSep 2026 → Dec 2026
June 1, 202471319Projected in-service dateJan 2024 → May 2024
June 1, 202480315First listedon the Future tab
June 1, 202480317First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first