Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Frio County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: BIG FOOT (FRIO County), BIG FOOT (FRIO County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Frio, TX: ERCOT queue, 4 active of 5. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Big Foot to Pearsall: Convert to 138 kV Convert the Big Foot to Dilley 69 kV line to 138 kV, rebuild the Dilley to Dilley Switch 69 kV line, and reroute the Big Foot to Dilley line from Dilley to Dilley Switch ERCOT project 80315 · utility no. 3821 · RPG 23RPG024 |
AEP TCC Tier 4 |
Planned Future tab |
138 | Feb 2028 | Big Foot to Pearsall Frio County |
Big Foot, Pearsall |
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Big Foot to Pearsall: Rebuild 69 kV line Rebuild 69 kV line from Big Foot to Dilley ERCOT project 55603 · utility no. 3821 |
AEP TCC Tier 3 |
Planned Cancelled tab |
69 | Nov 2022 actual 2025-05 |
Big Foot to Pearsall Frio County |
Big Foot, Pearsall |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 80315 | Projected in-service date | Dec 2027 → Feb 2028 |
| October 1, 2025 | 80315 | Projected in-service date | Dec 2026 → Dec 2027 |
| June 1, 2025 | 55603 | First listed | on the Cancelled tab |
| October 1, 2024 | 80315 | Projected in-service date | Sep 2026 → Dec 2026 |
| June 1, 2024 | 80315 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.