Lytle

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Frio County. First named in the release with data as of May 12, 2023.

Friocounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Frio, TX: ERCOT queue, 4 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Big Foot to Lytle: Convert to 138 kV
Convert the Big Foot to Lytle 69 kV line to 138 kV and interconnect Rowan Digital to the Lytle 138 kV station
ERCOT project 73063 · utility no. TP2022155
AEP TCC
Tier 4
Under Construction
Future tab
138 Feb 2027 Big Foot to Lytle
Medina / Frio County
Big Foot, Lytle

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202673063Moved between tabsCurrent-year planned → Future
October 1, 202673063Projected in-service dateNov 2026 → Feb 2027
June 1, 202673063Status as reportedPlanned → Under Construction
June 1, 202673063Projected in-service dateAug 2026 → Nov 2026
February 1, 202673063Moved between tabsFuture → Current-year planned
October 1, 202573063Projected in-service dateJun 2026 → Aug 2026
February 1, 202573063Projected in-service dateFeb 2026 → Jun 2026
October 1, 202473063Projected in-service dateSep 2025 → Feb 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.