Edith Clarke

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Foard County. First named in the release with data as of February 1, 2016.

Foardcounty as printed
345kV
AEP TNCutility
1projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 345 kV Station” — project 90035, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Foard, TX: ERCOT queue, 5 active of 5 · SPP queue, 0 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Edith Clarke: Expand 345 kV Station
Interconnect Seine BESS to the existing Edith Clarke 345 kV station
ERCOT project 90035 · utility no. TP2024193
AEP TNC
Tier 4
Planned
Future tab
345 Dec 2027 Edith Clarke
Foard County
Edith Clarke

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202690035Projected in-service dateJul 2027 → Dec 2027
October 1, 202590035Projected in-service dateDec 2027 → Jul 2027
February 1, 202590035First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.