Valley 345 kV Switch

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Fannin County. First named in the release with data as of June 1, 2024.

Fannincounty as printed
138, 345kV
ONCORutility
2projects listed

Also printed as: Valley Switch

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Fannin, TX: ERCOT queue, 3 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Valley Switch - Progress Park Switch 138 kV Line
Upgrade Valley Switch - Progress Park Switch 138 kV Line
ERCOT project 109805 · utility no. M3322 · RPG 25RPG040 · RTP 2024-N07
ONCOR
Tier 1
Planned
Future tab
138 Oct 2031 Valley Switch to Progress Park Switch
Fannin / Grayson County
Valley Switch, Progress Park Switch
Anna 345 kV Switch Rebuild and Anna Switch - Valley Switch 345 kV Line
Upgrade Anna Switch - Valley Switch 345 kV Line and Anna 345 kV switch Rebuild
ERCOT project 110284 · utility no. M3324 · RPG 25RPG040 · RTP 2024-NC31
ONCOR
Tier 1
Planned
Future tab
345 Mar 2033 Anna 345 kV Switch to Valley 345 kV Switch
Collin / Fannin County
Anna 345 kV Switch, Valley 345 kV Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109805First listedon the Future tab
July 13, 2026110284First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.