Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Erath County. First named in the release with data as of October 1, 2023.

Erathcounty as printed
345kV
LSTutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Erath, TX: ERCOT queue, 3 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Placeholder Station for Erath Solar POI
ERCOT project 75790
LST
Tier 4
Planned
Current-year planned tab
345 Aug 2026 No terminals printed
Erath County
Placeholder

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202675790Moved between tabsFuture → Current-year planned
June 1, 202475790Projected in-service dateJun 2025 → Aug 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.