Substation Scout

Rocksprings

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Edwards County. First named in the release with data as of October 1, 2019.

Edwardscounty as printed
69kV
AEP TCC, AEP TCC/AEP TNC, ETTutility
2projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rocksprings to Friess Ranch: Rebuild 69 kV line
Rehab Rocksprings to Sonora 69 kV line
ERCOT project 51005 · utility no. 2792 · RPG 19RPG018
AEP TCC/AEP TNC, ETT
Tier 3
Planned
Future tab
69 Apr 2027 Rocksprings to Friess Ranch
Edwards / Sutton County
Rocksprings, Friess Ranch
New Barksdale to Rocksprings: Rebuild 69 kV Line
Rebuild the Campwood to Rocksprings 69 kV line
ERCOT project 55605 · utility no. 3819 · RPG 24RPG009
AEP TCC
Tier 4
Planned
Future tab
69 Oct 2029 New Barksdale to Rocksprings
Edwards County
New Barksdale, Rocksprings

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202651005Projected in-service dateFeb 2027 → Apr 2027
June 1, 202655605Projected in-service dateNov 2028 → Oct 2029
June 1, 202551005Projected in-service dateDec 2026 → Feb 2027
October 1, 202455605Projected in-service dateAug 2028 → Nov 2028
June 1, 202451005Projected in-service dateJan 2025 → Dec 2026
June 1, 202455605Projected in-service dateJan 2026 → Aug 2028

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.