Campwood

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Edwards County. First named in the release with data as of October 1, 2020.

Edwardscounty as printed
69kV
AEP TCC/ETTutility
1projects listed

No HIFLD substation record has this name in this county.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Campwood to New Barksdale: Rebuild 69 kV Line
Rebuild the Campwood to Rocksprings 69 kV line
ERCOT project 55617 · utility no. 3820 · RPG 24RPG009
AEP TCC/ETT
Tier 4
Planned
Future tab
69 Oct 2029 Campwood to New Barksdale
Edwards County
Campwood, New Barksdale

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202655617Projected in-service dateNov 2028 → Oct 2029
October 1, 202455617Projected in-service dateAug 2028 → Nov 2028
June 1, 202455617Projected in-service dateJan 2026 → Aug 2028

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first