Substation Scout

Reata

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Eastland County. First named in the release with data as of October 1, 2023.

Eastlandcounty as printed
345kV
LSTutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Eastland, TX: ERCOT queue, 12 active of 12. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
This project will intercept the second circuit of a common tower at Reata station.
ERCOT project 75788
LST
Tier 4
Planned
Current-year planned tab
345 Dec 2025 No terminals printed
Eastland County
Reata

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202575788Moved between tabsFuture → Current-year planned

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first