Leon
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Eastland County. First named in the release with data as of February 1, 2015.
Eastlandcounty as printed
138kV
AEP TNC, LCRATSCutility
2projects listed
Also printed as: Leon Switch
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Eastland, TX: ERCOT queue, 12 active of 12. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Putnam to Leon: Rebuild 138 kV line Rehab the Putnam to Leon (Oncor) 138 kV line ERCOT project 55217 · utility no. 1859 |
AEP TNC Tier 4 |
Planned Future tab |
138 | Dec 2028 | Putnam to Leon Callahan / Eastland County |
Putnam, Leon |
| Leon Switch - Putnam Transmission Line Overhaul LCRA TSC will perform an overhaul on the 8.9-mile Leon Switch – Putnam (T727) 138-kV transmission line between Leon Switch existing structure #1/1 and Putnam existing structure #9/10. This project will increase reliability of the structures and conductor by ensuring that the transmission line meets or exceeds current NESC and LCRA TSC design standards. ERCOT project 77041 |
LCRATSC Tier 4 |
Planned Completed tab |
138 | May 2025 actual 2025-05 |
Leon Switch to Putnam Eastland County |
Leon Switch, Putnam |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2025 | 77041 | Moved between tabs | Future → Completed |
| February 1, 2025 | 55217 | Projected in-service date | Jul 2026 → Dec 2028 |
| February 1, 2025 | 77041 | Projected in-service date | Dec 2024 → May 2025 |
| June 1, 2024 | 55217 | Projected in-service date | Aug 2024 → Jul 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.