Asherton

Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Dimmit County. First named in the release with data as of February 1, 2015.

Dimmitcounty as printed
138kV
AEP TCC, AEP TCC/ETTutility
5projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 138 kV Station” — project 104611, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Dimmit, TX: ERCOT queue, 11 active of 12 · SPP queue, 1 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Asherton: Expand 138 kV Station
Interconnect Wilks data center load to the existing Asherton138 kV station
ERCOT project 104611 · utility no. Asherton
AEP TCC
Tier 4
Planned
Future tab
138 May 2028 Asherton
Dimmit County
Asherton
Asherton to West Batesville: Rebuild 138 kV Line
Rehab Asherton to West Batesville 138 kV line
ERCOT project 67915
AEP TCC/ETT
Tier 4
Planned
Future tab
138 Nov 2031 Asherton to West Batesville
Dimmit / Zavala County
Asherton, West Batesville
Asherton to Piloncillo: Rebuild 138 kV Line
Rehab the Asherton to Piloncillo 138 kV line
ERCOT project 73100
AEP TCC
Tier 4
Planned
Future tab
138 Jan 2028
actual 9999-01
Asherton to Piloncillo
Dimmit County
Asherton, Piloncillo
Asherton: Rebuild 138 kV station
Convert Asherton to Uvalde 69 kV to 138 kV, rebuild Asherton 138 kV station, build new Poblano 138 kV station
ERCOT project 76569 · RPG 23RPG007
AEP TCC
Tier 3
Under Construction
Future tab
138 May 2027 Asherton
Dimmit County
Asherton
Asherton to Uvalde: Convert to 138 kV
Convert Asherton to Uvalde 69 kV to 138 kV, rebuild Asherton 138 kV station, build new Poblano 138 kV station
ERCOT project 76576 · RPG 23RPG007
AEP TCC
Tier 3
Under Construction
Future tab
138 Jun 2027 Asherton to Uvalde
Dimmit / Uvalde County
Asherton, Uvalde

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202673100Projected in-service dateDec 2027 → Jan 2028
October 1, 202676569Status as reportedPlanned → Under Construction
October 1, 202676569Projected in-service dateAug 2027 → May 2027
October 1, 202676576Status as reportedPlanned → Under Construction
June 1, 2026104611First listedon the Future tab
June 1, 202676569Projected in-service dateApr 2027 → Aug 2027
February 1, 202676569Projected in-service dateDec 2026 → Apr 2027
February 1, 202676576Projected in-service dateMar 2026 → Jun 2027
October 1, 202567915Projected in-service dateNov 2030 → Nov 2031
October 1, 202576576Projected in-service dateDec 2026 → Mar 2026
February 1, 202567915Projected in-service dateDec 2028 → Nov 2030
February 1, 202576569Projected in-service dateMay 2026 → Dec 2026
February 1, 202576576Projected in-service dateMay 2026 → Dec 2026
June 1, 202473100Projected in-service dateMar 2025 → Dec 2027
June 1, 202476576First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.