Asherton
Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Dimmit County. First named in the release with data as of February 1, 2015.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 138 kV Station” — project 104611, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Dimmit, TX: ERCOT queue, 11 active of 12 · SPP queue, 1 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Asherton: Expand 138 kV Station Interconnect Wilks data center load to the existing Asherton138 kV station ERCOT project 104611 · utility no. Asherton |
AEP TCC Tier 4 |
Planned Future tab |
138 | May 2028 | Asherton Dimmit County |
Asherton |
| Asherton to West Batesville: Rebuild 138 kV Line Rehab Asherton to West Batesville 138 kV line ERCOT project 67915 |
AEP TCC/ETT Tier 4 |
Planned Future tab |
138 | Nov 2031 | Asherton to West Batesville Dimmit / Zavala County |
Asherton, West Batesville |
| Asherton to Piloncillo: Rebuild 138 kV Line Rehab the Asherton to Piloncillo 138 kV line ERCOT project 73100 |
AEP TCC Tier 4 |
Planned Future tab |
138 | Jan 2028 actual 9999-01 |
Asherton to Piloncillo Dimmit County |
Asherton, Piloncillo |
| Asherton: Rebuild 138 kV station Convert Asherton to Uvalde 69 kV to 138 kV, rebuild Asherton 138 kV station, build new Poblano 138 kV station ERCOT project 76569 · RPG 23RPG007 |
AEP TCC Tier 3 |
Under Construction Future tab |
138 | May 2027 | Asherton Dimmit County |
Asherton |
| Asherton to Uvalde: Convert to 138 kV Convert Asherton to Uvalde 69 kV to 138 kV, rebuild Asherton 138 kV station, build new Poblano 138 kV station ERCOT project 76576 · RPG 23RPG007 |
AEP TCC Tier 3 |
Under Construction Future tab |
138 | Jun 2027 | Asherton to Uvalde Dimmit / Uvalde County |
Asherton, Uvalde |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 73100 | Projected in-service date | Dec 2027 → Jan 2028 |
| October 1, 2026 | 76569 | Status as reported | Planned → Under Construction |
| October 1, 2026 | 76569 | Projected in-service date | Aug 2027 → May 2027 |
| October 1, 2026 | 76576 | Status as reported | Planned → Under Construction |
| June 1, 2026 | 104611 | First listed | on the Future tab |
| June 1, 2026 | 76569 | Projected in-service date | Apr 2027 → Aug 2027 |
| February 1, 2026 | 76569 | Projected in-service date | Dec 2026 → Apr 2027 |
| February 1, 2026 | 76576 | Projected in-service date | Mar 2026 → Jun 2027 |
| October 1, 2025 | 67915 | Projected in-service date | Nov 2030 → Nov 2031 |
| October 1, 2025 | 76576 | Projected in-service date | Dec 2026 → Mar 2026 |
| February 1, 2025 | 67915 | Projected in-service date | Dec 2028 → Nov 2030 |
| February 1, 2025 | 76569 | Projected in-service date | May 2026 → Dec 2026 |
| February 1, 2025 | 76576 | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2024 | 73100 | Projected in-service date | Mar 2025 → Dec 2027 |
| June 1, 2024 | 76576 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.