Substation Scout

Shaula

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in DeWitt County. First named in the release with data as of June 1, 2026.

DeWittcounty as printed
345kV
CPS/NOutility
1projects listed

Described as new. The quoted wording calls this substation new. “New Shaula 345kV Substation” — project 73025 title, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in DeWitt, TX: ERCOT queue, 5 active of 7. Same county, not the same substation.

Location

DeWitt County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, projects 73025 (release 2026-10) · OpenStreetMap: no feature with this name (Texas-wide name search) (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
New Shaula 345kV Substation
New Shaula 345kV Substation will be looped into the existing Elm Creek to STP circuit 1 transmission line.
ERCOT project 73025 · utility no. S-0970
CPS/NO
Tier 4
Planned
Future tab
345 Jan 2027 5380 to 5133, 5915
DeWitt County
Shaula

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202673025Moved between tabsCurrent-year planned → Future
July 13, 202673025Projected in-service dateMar 2026 → Jan 2027
February 1, 202673025Moved between tabsFuture → Current-year planned
June 1, 202573025Projected in-service dateNov 2026 → Mar 2026
February 1, 202573025Projected in-service dateNov 2024 → Nov 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.