Substation Scout

Pivot

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Dawson County. First named in the release with data as of October 1, 2025.

Dawsoncounty as printed
69kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Dawson, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Establish Pivot 138/69 kV Switch
Construct Pivot 138/69 kV Switch approved as part of 24RPG015
ERCOT project 99413 · utility no. R8800 · RPG 24RPG015
ONCOR
Tier 1
Planned
Current-year planned tab
69 Dec 2026 Lamesa to Pivot
Dawson County
Lamesa, Pivot

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202699413Moved between tabsFuture → Current-year planned
February 1, 202699413Projected in-service dateNov 2026 → Dec 2026
October 1, 202599413First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.