Ozona

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Crockett County. First named in the release with data as of February 1, 2015.

Crockettcounty as printed
69kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Crockett, TX: ERCOT queue, 9 active of 10. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Ozona: Rebuild 69 kV station
Replace existing Ozona 69 kV station with a new 69 kV ring bus
ERCOT project 49556 · utility no. 2780
AEP TNC
Tier 4
Planned
Future tab
69 Jan 2029 Ozona
Crockett County
Ozona

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202649556Projected in-service dateMar 2028 → Jan 2029
June 1, 202649556Projected in-service dateJun 2027 → Mar 2028
June 1, 202449556Projected in-service dateOct 2024 → Jun 2027

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.