Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Crockett County. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: FRIEND RANCH (CROCKETT County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Crockett, TX: ERCOT queue, 9 active of 10. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Friend Ranch: Build new 138 kV Terminal Interconnect Blue Sky Solar to the Friend Ranch 138 kV Station ERCOT project 68254 |
AEP TNC Tier 4 |
Planned Future tab |
138 | May 2027 | Friend Ranch Crockett County |
Friend Ranch |
| Carver to Friend Ranch: Rebuild 138 kV Line Rebuild the Carver to Friend Ranch 138 kV line ERCOT project 91906 · utility no. TP2025168 · RPG H.B. 5066 |
AEP TNC Tier 3 |
Planned Future tab |
138 | Nov 2028 | Carver to Friend Ranch Sutton / Crockett County |
Carver, Friend Ranch |
| Friend Ranch to Illinois #4: Convert to 138 kV Convert the Friend Ranch to Illinois #4 69 kV line to 138 kV ERCOT project 99749 · RPG H.B. 5066 |
AEP TNC Tier 2 |
Planned Future tab |
138 | Nov 2029 | Friend Ranch to Illinois #4 Crockett County |
Friend Ranch, Illinois #4 |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 91906 | Projected in-service date | May 2028 → Nov 2028 |
| June 1, 2026 | 68254 | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 68254 | Projected in-service date | Nov 2026 → May 2027 |
| June 1, 2026 | 91906 | Projected in-service date | Dec 2030 → May 2028 |
| February 1, 2026 | 68254 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99749 | Projected in-service date | Dec 2030 → Nov 2029 |
| October 1, 2025 | 99749 | First listed | on the Future tab |
| June 1, 2025 | 91906 | First listed | on the Future tab |
| February 1, 2025 | 68254 | Projected in-service date | Nov 2024 → Nov 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.