Ollin

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Crane County. First named in the release with data as of February 1, 2019.

Cranecounty as printed
138kV
AEP TNCutility
2projects listed

Described as new. The quoted wording calls this substation new. “new Ollin 138 kV station” — project 45155 description, as the utility reported it

Reported complete. Project 45155 is on the Completed tab (actual in-service 2025-06); Project 45174 is on the Completed tab (actual in-service 2025-12), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Crane, TX: ERCOT queue, 13 active of 14. Same county, not the same substation.

Location

Crane County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: TPIT lists 45155 and 45174 on the Completed tab: In-Service, actual dates 2025-06 and 2025-12. The progress report lists the station as 'Ollin 69-kV', built to 138-kV standards.

Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, projects 45155, 45174 (release 2026-10) · AEP Texas construction progress report (North Division), PUCT Project 57477 item 149 (2025-05-15), North Division, Ollin entries · OpenStreetMap: Crane-area substations (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Ollin: Build 138 kV station
Construct new Ollin 138 kV station
ERCOT project 45155 · utility no. 2752 · RPG 19RPG013
AEP TNC
Tier 4
In-Service
Completed tab
138 Jun 2025
actual 2025-06
Ollin
Crane County
Ollin
Ollin to LCRA Crane: Partial Build, Partial Rebuild, and Conversion
Build new Ollin 138 kV station; partial build, rebuild, and conversion to 138 kV of Ollin to LCRA Crane; and rebuild McElroy to Sage
ERCOT project 45174 · utility no. 2767 · RPG 19RPG013
AEP TNC
Tier 4
In-Service
Completed tab
138 Jan 2026
actual 2025-12
Ollin to LCRA Crane
Crane County
Ollin, Crane

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202645174Moved between tabsCurrent-year planned → Completed
July 13, 202645174Status as reportedPlanned → In-Service
February 1, 202645174Projected in-service dateSep 2025 → Jan 2026
October 1, 202545155Moved between tabsCurrent-year planned → Completed
October 1, 202545155Status as reportedUnder Construction → In-Service
October 1, 202545174Projected in-service dateApr 2025 → Sep 2025
June 1, 202545155Moved between tabsFuture → Current-year planned
June 1, 202545174Moved between tabsFuture → Current-year planned
February 1, 202545155Status as reportedPlanned → Under Construction
February 1, 202545155Projected in-service dateDec 2024 → Jun 2025
June 1, 202445174Projected in-service dateJan 2025 → Apr 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.