Kinnison

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Crane County. First named in the release with data as of October 1, 2019.

Cranecounty as printed
69, 138kV
AEP TNCutility
2projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 138 kV station” — project 50845, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Crane, TX: ERCOT queue, 13 active of 14. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Kinnison: Expand 138 kV station
Build Heron 138 kV station with a 138/69 kV auto, expand the Kinnison 138 kV station, expand the Sage 69 kV station, rebuild Heron to Ollin and convert to a 138 kV line, and rebuild Kinnison to Sage 69 kV line
ERCOT project 50845 · utility no. 2797
AEP TNC
Tier 3
Under Construction
Completed tab
138 Jan 2026
actual 2025-07
Kinnison
Crane County
Kinnison
Kinnison to Sage: Rebuild 69 kV line
Build Heron 138 kV station with a 138/69 kV auto, expand the Kinnison 138 kV station, expand the Sage 69 kV station, rebuild Heron to Ollin and convert to a 138 kV line, and rebuild Kinnison to Sage 69 kV line
ERCOT project 51012 · utility no. 2823
AEP TNC
Tier 3
In-Service
Completed tab
69 Jan 2026
actual 2025-11
Kinnison to Sage
Crane County
Kinnison, Sage

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202650845Moved between tabsCurrent-year planned → Completed
July 13, 202651012Moved between tabsCurrent-year planned → Completed
July 13, 202651012Status as reportedPlanned → In-Service
February 1, 202650845Projected in-service dateJun 2025 → Jan 2026
February 1, 202651012Projected in-service dateAug 2025 → Jan 2026
October 1, 202550845Projected in-service dateMay 2025 → Jun 2025
October 1, 202551012Projected in-service dateMay 2025 → Aug 2025
June 1, 202550845Moved between tabsFuture → Current-year planned
June 1, 202550845Projected in-service dateFeb 2025 → May 2025
June 1, 202551012Moved between tabsFuture → Current-year planned
June 1, 202551012Projected in-service dateFeb 2025 → May 2025
February 1, 202550845Status as reportedPlanned → Under Construction
June 1, 202450845Projected in-service dateJun 2025 → Feb 2025
June 1, 202451012Projected in-service dateJun 2025 → Feb 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.