Howard Rd
Named in 2 listed projects in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2025.
Described as new. The quoted wording calls this substation new. “new 765kV Howard Rd Switching Station” — project 102068 title, as the utility reported it
Also printed as: Howard Rd Switching
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.
Location
Bexar County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: Names vary across sources: 'Howard Rd Switching Station' (TPIT), 'future Howard Rd. Station' (CPS), 'existing Howard Substation' (AEP). The 2023 CPS brochure maps a separate, earlier Howard Rd. switching station project (345 kV area, outlined property near Watson Rd and SH 16, construction Oct 2023 - May 2025); OSM tags a 345 kV CPS 'Howard Substation' (way 1428417852). The 765 kV yard would connect into that station, but no source prints where the 765 kV yard itself sits, so the existing station's point is not used.
Sources: AEP Texas, Blu Lacy - Howard 765 kV Transmission Line Project (2026) · CPS Energy, Howard - Solstice Transmission Line Project brochure (2025-08), p.1 · CPS Energy, Howard Rd. Switching Station and Transmission Line Project brochure (2023-10-20), p.2 Project Location Map · ERCOT TPIT, projects 102068 and 75255A (release 39, 2026-10-01). Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Construct a new 765kV Howard Rd Switching Station with two 765/345kV autotransformers connnection into the two new positions at Howard Rd 345kV station. Also construct the station with 4 line terminals to accommodate the full 765kV build out. The station w ERCOT project 102068 |
CPS/AEP Tier 1 |
Planned Future tab |
765 | Dec 2030 | No terminals printed | Howard Rd Switching |
| San Antonio South Reliability RPG Project Construct a new, 50-mile Howard Rd to San Miguel 345kV double circuit transmission line with a normal and emergency rating of at least 1982 MVA per circuit; this transmission line will require approximately 50 mile of new Right of Way (ROW). ERCOT project 75255A · RPG 22RPG048 |
CPS/CPS, STEC Tier 1 |
Planned Future tab |
345 | Nov 2027 | 5231 to 5901 Bexar / Atascosa County |
Howard Rd, San Miguel |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 102068 | Projected in-service date | Jan 2031 → Dec 2030 |
| July 13, 2026 | 75255A | Projected in-service date | Jun 2027 → Nov 2027 |
| October 1, 2025 | 102068 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.