Holleman
Named in 2 listed projects in ERCOT’s transmission project tracking workbook. First named in the release with data as of October 1, 2023.
Described as new. The quoted wording calls this substation new. “New Holleman Substation” — project 70299 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Brazos, TX: ERCOT queue, 1 active of 2. Same county, not the same substation.
Location
30.5805, -96.3224 · Brazos County, TX · view on a map
Parcel or address in a filing. A filing names the parcel or address; the point is its center. Accurate to about ±250 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: Address printed in Bryan Texas Utilities' Request for Bid 032-09-26 ('Holleman Substation Construction'): 11720 Old Wellborn Road, College Station, TX 77845. Point is the US Census geocoder's match for that address (Public_AR_Current, address-range interpolation on Old Wellborn Rd), not a parcel centroid; Nominatim's interpolation agrees within 5 m. The yard may be set back from the road: +/- ~250 m. Consistent with the scope ('interjects into the existing South Switch to Dowling Road line'): OSM Dowling Road Substation (way 510128606) is 1.2 km and BTU South Switching Station (way 398989843) 1.8 km away.
Note: The address comes from a procurement aggregator's copy of BTU's bid notice; BTU's own bid document was not opened. The listing gives two bid deadlines (July 29 and Aug. 14, 2026).
County: the Census county at this point.
Sources: HigherGov listing of BTU Request for Bid 032-09-26, Holleman Substation Construction (2026-06-17) · US Census geocoder: 11720 Old Wellborn Rd, College Station, TX 77845 (Public_AR_Current) · OpenStreetMap: Dowling Road Substation, BTU South Switching Station (OSM base 2026-11-20) · ERCOT TPIT, project 70299 (release 39, 2026-10-01). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| BRYN_SOSW-HLMN-DWLRD_Upgrade Upgrade Dowling Road to Holleman 138kV Line ERCOT project 104249B |
BRYN Tier 4 |
Planned Future tab |
138 | Jun 2030 | BTU Dowling Road to BTU Holleman Brazos County |
Dowling Road, Holleman |
| New Holleman Substation ERCOT project 70299 |
BRYN Tier 4 |
Not reported Future tab |
138 | Jun 2028 | No terminals printed | Holleman |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 104249B | Projected in-service date | Jun 2028 → Jun 2030 |
| October 1, 2026 | 70299 | Projected in-service date | Jun 2027 → Jun 2028 |
| June 1, 2026 | 104249B | First listed | on the Future tab |
| June 1, 2026 | 70299 | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 70299 | Projected in-service date | Dec 2026 → Jun 2027 |
| February 1, 2026 | 70299 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 70299 | Projected in-service date | Dec 2025 → Dec 2026 |
| June 1, 2024 | 70299 | Projected in-service date | Feb 2025 → Dec 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.