Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Comal County. First named in the release with data as of February 1, 2024.

Comalcounty as printed
138kV
NBUutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Comal, TX: ERCOT queue, 2 active of 4. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
SW3379 Replacement
Replacing existing 1200 Amp switch and 1800 Amp bypass jumper with new 3000 Amp switch.
ERCOT project 78414
NBU
Tier 4
Planned
Completed tab
138 Oct 2025
actual 2025-09
No terminals printed
Comal County
Amp

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202678414Moved between tabsCurrent-year planned → Completed
October 1, 202578414Moved between tabsFuture → Current-year planned
October 1, 202578414Projected in-service dateMay 2026 → Oct 2025
February 1, 202578414Projected in-service dateMar 2026 → May 2026
October 1, 202478414Projected in-service dateJul 2025 → Mar 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.