Renner
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Collin County. First named in the release with data as of February 1, 2015.
Collincounty as printed
138kV
ONCORutility
2projects listed
Also printed as: Renner Switch
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Collin, TX: ERCOT queue, 4 active of 5. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Renner Switch 138kV Capacitor Bank Install Capacitor Banks at Renner switch ERCOT project 92849 · utility no. M4021 |
ONCOR Tier 4 |
Planned Current-year planned tab |
138 | May 2026 | Renner Switch to Renner Switch Collin County |
Renner Switch |
| Renner Switch – Plano West Switch 138 kV Double-Circuit Line Upgrade Renner Switch – Plano West Switch 138 kV Double-Circuit Line ERCOT project 92867 · utility no. M4246 |
ONCOR Tier 4 |
Planned Future tab |
138 | Dec 2029 | Renner to Plano West Collin County |
Renner, Plano West |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 92867 | Projected in-service date | May 2029 → Dec 2029 |
| June 1, 2026 | 92867 | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 92867 | Projected in-service date | May 2026 → May 2029 |
| February 1, 2026 | 92849 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 92849 | Projected in-service date | May 2028 → May 2026 |
| February 1, 2026 | 92867 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 92849 | Projected in-service date | May 2026 → May 2028 |
| June 1, 2025 | 92849 | First listed | on the Future tab |
| June 1, 2025 | 92867 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.