Chelsea Switch

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Collin County. First named in the release with data as of June 1, 2026.

Collincounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Collin, TX: ERCOT queue, 4 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Chelsea 138 kV Switch
ERCOT project 92625 · utility no. M5019
ONCOR
Tier 4
Planned
Future tab
138 May 2027 Chelsea Switch
Collin County
Chelsea Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202692625Moved between tabsCurrent-year planned → Future
October 1, 202692625Projected in-service dateJun 2026 → May 2027
July 13, 202692625Projected in-service dateApr 2026 → Jun 2026
February 1, 202692625Moved between tabsFuture → Current-year planned
June 1, 202592625First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.