Firerock

Named in 0 listed projects in ERCOT’s transmission project tracking workbook, in Coleman County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2025.

Colemancounty as printed
138kV
AEP TNCutility
0projects listed

Projects cancelled. Every project naming Firerock is on the Cancelled tab of ERCOT's workbook.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Coleman, TX: ERCOT queue, 7 active of 9. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

No projects.

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Firerock: Install New 138/69 kV Autotransformer
Install new 138/69 kV autotransformer at the Firerock 138/69 kV station
ERCOT project 90020 · utility no. TP2022133
AEP TNC
Tier 4
Planned
Cancelled tab
138 May 2027 Firerock
Coleman County
Firerock

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202690020Moved between tabsFuture → Cancelled
February 1, 202590020First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first