Pecan Bayou

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Callahan County. First named in the release with data as of June 1, 2026.

Callahancounty as printed
138kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Callahan, TX: ERCOT queue, 7 active of 7. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Pecan Bayou: 138 kV Circuit Breaker Addition
Install two 138 kV circuit breakers at the Pecan Bayou 138 kV station
ERCOT project 99648 · utility no. TP2023323
AEP TNC
Tier 4
Planned
Future tab
138 Oct 2028 Pecan Bayou
Callahan County
Pecan Bayou

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202699648Projected in-service dateMay 2027 → Oct 2028
October 1, 202599648First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.