Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Calhoun County. First named in the release with data as of October 1, 2026.

Calhouncounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Calhoun, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Cangrejo to Dacosta: Rebuild 138 kV Line
Rehab 138 kV line from Cangrejo to Dacosta
ERCOT project 69253 · RPG 21RPG002
AEP TCC
Tier 1
Planned
Current-year planned tab
138 Nov 2026 Cangrejo to Dacosta
Calhoun County
Cangrejo, Dacosta

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202669253Moved between tabsFuture → Current-year planned
October 1, 202569253Projected in-service dateMay 2026 → Nov 2026
June 1, 202469253Projected in-service dateNov 2025 → May 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.