Substation Scout

Brookhollow

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Calhoun County. First named in the release with data as of October 1, 2022.

Calhouncounty as printed
69kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Calhoun, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Brookhollow to Cangrejo: Rebuild 69 kV Line
Rebuild 69 kV line from Brookhollow to Cangrejo
ERCOT project 78545 · RPG 21RPG002 · RTP 2019-C2
AEP TCC
Tier 1
Planned
Future tab
69 Nov 2028 Brookhollow to Cangrejo
Calhoun County
Brookhollow, Cangrejo

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202578545Projected in-service dateDec 2027 → Nov 2028
February 1, 202578545Projected in-service dateNov 2028 → Dec 2027
June 1, 202478545First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first