Euclid

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Caldwell County. First named in the release with data as of October 1, 2024.

Caldwellcounty as printed
345, 765kV
LCRATSCutility
3projects listed

Expansion at an existing substation: new voltage level. The quoted wording describes a yard, bus or conversion at a voltage this substation is not otherwise shown at. “construct a new Euclid 765-kV yard” — project 104118, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Caldwell, TX: ERCOT queue, 16 active of 17. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
LCRATSC Euclid 765-kV Substation Addition
This project will construct a new Euclid 765-kV yard adjacent to the existing Euclid 345-kV Substation (PLC-7694) and install two new 765/345-kV autotransformers.
ERCOT project 104118 · RPG 26RPG001
LCRATSC
Tier 1
Planned
Future tab
765 Jun 2031 No terminals printed
Caldwell County
Euclid
LCRATSC Euclid to Hillje (Morely) 765kV Transmission Line Addition
Construct a new 765-kV single-circuit transmission line from Euclid Substation to a point-of-interconnection (POI) with CenterPoint Energy (CNPE).
ERCOT project 104732 · RPG 26RPG001
LCRATSC
Tier 1
Planned
Future tab
765 Jun 2031 Euclid to Morely
Caldwell / Wharton County
Euclid, Morely
Euclid_Substation_Addition_Updated
LCRA TSC provide a new transmission point of interconnection by constructing a new 345-kV substation and cut-in T510 Hutto - Zorn. T510 will also be looped into the new Limmer 345-kV substation
ERCOT project 85947
LCRATSC
Tier 4
Planned
Current-year planned tab
345 Nov 2026
actual 2026-11
No terminals printed
Caldwell County
Euclid, Limmer

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 2026104118First listedon the Future tab
June 1, 2026104732First listedon the Future tab
February 1, 202685947Moved between tabsFuture → Current-year planned
October 1, 202485947First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.