Substation Scout

GLOBAL

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of February 1, 2025.

Brazoriacounty as printed
138kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Clute to Velasco Ckt.82 Upgrades RPG
Upgrade Ckt.82D GLOBAL to Velasco to increase thermal limits.
ERCOT project 90242D · RPG 24RPG012
CNP
Tier 4
Planned
Future tab
138 May 2027 GLOBAL to Velasco
Brazoria County
GLOBAL, Velasco

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202690242DProjected in-service dateMay 2026 → May 2027
February 1, 202590242DFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first