Substation Scout

CASCAD

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Brazoria County. First named in the release with data as of October 1, 2023.

Brazoriacounty as printed
345kV
CNPutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Brazoria, TX: ERCOT queue, 54 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
New 345kV Savannah (SAV) substation for generator interconnection to Cascade Solar (23INR0091).
Install generator lead from Savannah (SAV) substation to CASCAD (CSC) customer substation (23INR0091).
ERCOT project 75830B
CNP
Tier 4
Planned
Future tab
345 May 2028 Savannah to CASCAD
Brazoria County
Savannah, CASCAD

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202675830BProjected in-service dateDec 2027 → May 2028
February 1, 202675830BProjected in-service dateDec 2026 → Dec 2027
October 1, 202575830BProjected in-service dateJan 2026 → Dec 2026
June 1, 202575830BProjected in-service dateDec 2025 → Jan 2026
October 1, 202475830BProjected in-service dateMay 2025 → Dec 2025
June 1, 202475830BProjected in-service dateJun 2025 → May 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first