Substation Scout

Faraday

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Borden County. First named in the release with data as of October 1, 2025.

Bordencounty as printed
345kV
ONCOR, WETTutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Borden, TX: ERCOT queue, 17 active of 19 · SPP queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
WETT project to loop Faraday station in the existing Long Draw to Scurry 345 kV double circuit transmission line approved as part of 24RPG015.
ERCOT project 100136 · RPG 24RPG015
WETT
Tier 1
Planned
Future tab
345 May 2029 Faraday to Faraday
Borden County
Faraday
Lamesa - Faraday 345 kV Double Circuit Line
Oncor and WETT joint project to construct the Lamesa (Oncor) - Faraday (WETT) 345 kV DCKT Line approved as part of 24RPG015
ERCOT project 99419 · utility no. R8792 · RPG 24RPG015
ONCOR
Tier 1
Planned
Future tab
345 May 2029 Lamesa to Faraday
Dawson / Borden County
Lamesa, Faraday

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 2026100136Projected in-service dateDec 2029 → May 2029
October 1, 2025100136First listedon the Future tab
October 1, 202599419First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.