Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Bexar County. First named in the release with data as of February 1, 2019.

Bexarcounty as printed
138kV
CPS/NOutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Quintana Rd to South San Rebuild
Rebuild 1.3 miles of 138 kV transmission line form Quintana Rd substation to South San substation.
ERCOT project 45125 · utility no. T-0271
CPS/NO
Tier 4
Planned
Future tab
138 May 2028 5350 to 5385
Bexar County
Quintana Rd, South San

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202545125Projected in-service dateMay 2025 → May 2028
June 1, 202445125Projected in-service dateJun 2031 → May 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.