Martinez-Skyline

Named in 0 listed projects in ERCOT’s transmission project tracking workbook, in Bexar County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.

Bexarcounty as printed
138kV
CPSutility
0projects listed

Projects cancelled. Every project naming Martinez-Skyline is on the Cancelled tab of ERCOT's workbook.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

No projects.

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Converse - New 138kV Substation
Loop new 138kV substation into future 138kV Martinez to Skyline transmission line
ERCOT project 15TPIT0004 · utility no. S-0601
CPS
Tier 4
Planned
Cancelled tab
138 Jun 2032 Converse to Martinez-Skyline
Bexar County
Converse, Martinez-Skyline

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202515TPIT0004Moved between tabsFuture → Cancelled
February 1, 202515TPIT0004First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.