Substation Scout

Eastside

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Bexar County. First named in the release with data as of June 1, 2026.

Bexarcounty as printed
138, 345kV
CPS, CPS/NOutility
2projects listed

Described as new. The quoted wording calls this substation new. “New Eastside Switching Station” — project 84898 title, as the utility reported it

Also printed as: Eastside Switching

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.

Location

Bexar County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: ERCOT's May 2026 board report calls it 'the existing Eastside 345/138-kV substation' (adding an autotransformer), while TPIT 84898 still lists a new Eastside Switching Station, Planned, ISD 2030-01. CPS's public materials (Dec 2024 / Jan 2025 open house) show only a study area and site criteria (about 100 acres, out of floodplain, access to the existing lines); no selected site was published. OSM has no Eastside station; OSM Beck Road Substation (way 174509135) is the reference station, not this one. TPIT's RPG field reads '23RPG032: San Antonio South Reli...'; ERCOT's review documents for this station are the 2024 'CPS Eastside 345/138-kV Switching Station Project' series.

Sources: ERCOT Independent Review, CPS Eastside 345/138-kV Switching Station Project, RPG July 2024 (2024-07-12), slide 5 · CPS Energy, Eastside Switchyard Project page (n/a) · CPS Energy, Eastside Switchyard Project open house displays (2025-01), site requirements; study area map · ERCOT Board item 5.1 (25RPG013/25RPG017) (2026-05-22), p.2 · ERCOT TPIT, projects 84898 and 100676 (release 39, 2026-10-01). Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install a 50MVAr Capacitor Bank at the future Eastside Substation
ERCOT project 100676 · utility no. S-1049 · RPG 24RPG004
CPS/NO
Tier 2
Planned
Future tab
138 Jan 2030 5136
Bexar County
Eastside
New Eastside Switching Station
ERCOT project 84898 · utility no. T-0399 · RPG 23RPG032: San Antonio South Reli
CPS
Tier 1
Planned
Future tab
345 Jan 2030 No terminals printed
Bexar County
Eastside Switching

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026100676Projected in-service dateJun 2029 → Jan 2030
July 13, 202684898Projected in-service dateJun 2029 → Jan 2030
October 1, 2025100676First listedon the Future tab
June 1, 202484898First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →