Brooks
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Bexar County. First named in the release with data as of February 1, 2015.
Bexarcounty as printed
138kV
CPSutility
3projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Chavaneaux_Chavaneaux Tap Rebuild (Brooks to Chavaneaux ckt) Rebuild 138 kV transmission from Chavaneaux to Chavaneaux Tap. This rebuild is for Brooks to Chavaneaux ckt. ERCOT project 15TPIT0031 · utility no. T-0260 |
CPS Tier 4 |
Planned Future tab |
138 | May 2030 | Brooks to Chavaneaux Bexar County |
Brooks, Chavaneaux |
| CPSE_Brooks to Chavaneaux MLSE Upgrade terminals at Brooks and Chavaneaux to ensure a 1364 A rating (minimum) ERCOT project 4320 · utility no. S-0733 |
CPS Tier 4 |
Not reported Future tab |
138 | May 2030 | Brooks to Chavaneaux Bexar County |
Brooks, Chavaneaux |
| CPSE_Brooks_MLSE Upgrade terminal at Brooks and ensure a rating of 2000 A (minimum) at both Braunig and Brooks terminals ERCOT project 4323 · utility no. S-0669 |
CPS Tier 4 |
In-Service Completed tab |
138 | Apr 2025 actual 2025-04 |
Braunig to Brooks Bexar County |
Braunig, Brooks |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 15TPIT0031 | Projected in-service date | Jan 2030 → May 2030 |
| July 13, 2026 | 4320 | Projected in-service date | Jan 2030 → May 2030 |
| October 1, 2025 | 15TPIT0031 | Projected in-service date | Jun 2027 → Jan 2030 |
| October 1, 2025 | 4320 | Projected in-service date | Dec 2026 → Jan 2030 |
| October 1, 2025 | 4323 | Moved between tabs | Future → Completed |
| October 1, 2025 | 4323 | Projected in-service date | May 2026 → Apr 2025 |
| June 1, 2025 | 4323 | Projected in-service date | Jan 2032 → May 2026 |
| February 1, 2025 | 4323 | First listed | on the Future tab |
| June 1, 2024 | 15TPIT0031 | Projected in-service date | Jun 2026 → Jun 2027 |
| June 1, 2024 | 4323 | No longer listed | future |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.