Substation Scout

5400 and 5475

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Bexar County. First named in the release with data as of June 1, 2022.

Bexarcounty as printed
345kV
CPS/NOutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Bexar, TX: ERCOT queue, 22 active of 23. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
CPSE_345KV_Howard_Switching_Station,CPSE_Hamilton_to_MedCtr_Upgrade
Looping of 345KV Howard Rd switching station into existing Cagnon to AVR and Cagnon to Spruce 34KV lies. The switching station will have 2 600MVA 345KV/138KV autotransformers.
ERCOT project 67992C
CPS/NO
Tier 3
In-Service
Completed tab
345 May 2025
actual 2025-04
5056 to 5400 and 5475
Bexar County
5400 and 5475

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202667992CStatus as reportedPlanned → In-Service
June 1, 202567992CMoved between tabsFuture → Completed
June 1, 202467992CProjected in-service dateJun 2025 → May 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first