Substation Scout

Tynan

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Bee County. First named in the release with data as of October 1, 2026.

Beecounty as printed
69kV
AEP TCCutility
1projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 69 kV Station” — project 111219, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Bee, TX: ERCOT queue, 10 active of 12. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Tynan: Expand 69 kV Station
Interconnect Honeycomb Solar and Storage to the Tynan 69 kV station
ERCOT project 111219 · utility no. TP2023005
AEP TCC
Tier 4
Planned
Current-year planned tab
69 Jun 2026 Tynan
Bee County
Tynan

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026111219First listedon the Current-year planned tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.