Settlers
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Bastrop County. First named in the release with data as of June 1, 2025.
Bastropcounty as printed
138, 345kV
LCRATSCutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Bastrop, TX: ERCOT queue, 14 active of 16. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Settlers Autotransformer Addition Construct a new 345-kV yard adjacent to the existing 138-kV Settlers Substation and cut-in to the Austrop - Lost Pines 345-kV double-circuit transmission line (owned by Austin Energy). LCRA TSC will install two 345/138-kV autotransformers at Settlers Substation. ERCOT project 109749 |
LCRATSC Tier 3 |
Planned Future tab |
345 | May 2029 | Settlers Bastrop County |
Settlers |
| LCRATSC_Settlers Substation Upgrade Settlers Substation Addition project will construct a new substation connecting to LCRA TSC owned 138-kV transmission lines T171 Austrop to Sim Gideon and T231 Bastrop to Webberville via a hard tap installation. In this project, LCRA TSC will upgrade the hard tap installation to a breakered facility. ERCOT project 91289 · utility no. PLC-6691 |
LCRATSC Tier 4 |
Planned Current-year planned tab |
138 | Oct 2026 | No terminals printed Bastrop County |
Settlers |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 109749 | First listed | on the Future tab |
| July 13, 2026 | 91289 | Moved between tabs | Future → Current-year planned |
| July 13, 2026 | 91289 | Projected in-service date | Apr 2027 → Oct 2026 |
| February 1, 2026 | 91289 | Projected in-service date | May 2026 → Apr 2027 |
| June 1, 2025 | 91289 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.