Substation Scout

Pine Path

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Bastrop County. First named in the release with data as of October 1, 2025.

Bastropcounty as printed
138kV
LCRATSCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Bastrop, TX: ERCOT queue, 14 active of 16. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Pine Path Substation Addition
Construct a new 138-kV substation to cut-in on T670 to serve new customer load in the BBEC service territory.
ERCOT project 99924
LCRATSC
Tier 4
Planned
Future tab
138 Dec 2027 No terminals printed
Bastrop County
Pine Path

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202699924Projected in-service dateJun 2027 → Dec 2027
October 1, 202599924First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.