County Line

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Bastrop County. First named in the release with data as of July 13, 2026.

Bastropcounty as printed
138kV
LCRATSCutility
2projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Bastrop, TX: ERCOT queue, 14 active of 16. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
County Line - Garfield Transmission Line Addition
LCRA TSC will construct a new 138-kV transmission line between County Line and Garfield substations. Project marked as conceptual for the moment as this project is also identified as an LCP Upgrade project to support Batch Zero Base Load.
ERCOT project 110162
LCRATSC
Tier 4
Conceptual
Future tab
138 Jun 2028 County Line to Garfield
Bastrop County
County Line, Garfield
County Line Dynamic Reactive Substation Upgrade
Install reactive support at the County Line 138-kV Substation. This is an LCP Upgrade project to support Batch Zero Base Load
ERCOT project 110166
LCRATSC
Tier 4
Conceptual
Future tab
138 Oct 2027 County Line
Bastrop County
County Line

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110162First listedon the Future tab
July 13, 2026110166First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.